Construction of the connecting channel from Kamnik to Smartno v Tuhinju
Soteska
The contractor has this week continued to work on the regional road R2-414 / 1349 Kamnik-Ločica. Dispose of the faecal sewage DN 300 and DN 150. Because water is part of a partial road closures. After the construction of each section will be an area of partial closures slide toward Tuhinju. In this week's planned continuation of the work.
Srednja vas
There was fine laying asphalt on the two public channels, which were until now asphalted only with rough asphalt.
Kavran
The contractor continued to work on a range of Kavran. Currently, laying the pressure sewerage and water supply DN 150. There was fine laying asphalt on the section from the source in the village of Nevlje against Kavran, which has so far been laid only a rough asphalt. Because it is part of a partial road closure, which moves in the direction of Kamnik. Regulating the agricultural land on which construction took place. In this week's planned continuation of the work.
Šmartno v Tuhinju
The contractor has paved public path along which conducted the installation of water supply wells Šmartno. There were finishing work on buildings pumping station and reservoir. In this week's planned continuation of the work.