Construction of the sewer in the Municipality of Komenda continues

15 September 2016
Construction of the sewer in the Municipality of Komenda continues
Moste

In the Municipality of Komenda is working on a project for drainage and wastewater treatment in the area of ​​Domžale-Kamnik, sewage Waterfront in the municipality of Komenda, in the month of September are carried out according to the schedule. Works are currently underway on the three sections, bridge, Suhadole and Montenegro (the racetrack).

In Moste, the work is carried out between residential houses on the canal MO4. Part somewhat complicates the difficult terrain accessible through orchards with houses on one arm and the rehabilitation of water supply works, financed by the Municipality of Komenda, on the second leg.

Šolska pot in Moste which leads past the church Sv. Boštjan, was completed and covered with asphalt

In the village Suhadole at the beginning of the month prior to asphalting sought the most appropriate way for proper drainage from underground streams. In the first measure, it depends on the very slope and location of the road and the other mainly on the possibility of the excavation and installation of pipes, which serve as sinks. Needs have been collusion with landowners who still have a percolator on their land allowed. Otherwise, it was in some sections need to look for alternative solutions.

In the middle of September in the Suhadole began with asphalt, in the first phase with coarse asphalt. By the end of September, paving the Suhadole completed.

Work in the Hippodrome, on the so-called section Gora continue. The pumping station has been built. The parts are moved to the start of the path between the stream and the Prince's racecourse and thus enabled during the construction of the children the safe way to school near the building of the racecourse. School pupils trail running smoothly and without problems.

Work on this section complicates the earth is a place of laying pipes of clay and the wet weather does not provide sufficient strength and stability, and therefore require filling with sand and drainage.